Works at Council’s administration centre

Council’s Administration Building will have its roof cleaned, repaired, and re-pointed over the next few weeks. These works will leave the building looking refreshed, but there will be some minor impacts during this time.
What’s happening and when?
👉 17–21 November: Scaffolding will be installed around all four sides of the building. ✅ Main entrance will remain open
👉 22–23 November: Roof cleaning expected to commence.
👉 24–28 November: Repairs and re-pointing underway.
👉 1–5 December: Scaffolding removed.
If you’re visiting Council during this time, please take extra care around the building and follow any signage or directions from staff. Your safety is important to us!
Please note: This schedule is weather dependent and may change if issues arise during repairs. There’s also a chance the work will finish earlier than planned.
Thank you for your patience as we improve our facilities.