Works update – 15 April 2026

Work crews are continuing to upgrade sections of Clarence Way.

A pavement upgrade on the Medhurst Quarry section of the road south of Bonalbo has started and will be ongoing for the next three weeks.

Another crew working on Clarence Way north of Bonalbo has finished sealing a section of the road, with line-marking still to completed.

Both jobs are expected to be finalised in May.

Meanwhile, planning work has started on an upcoming project to upgrade of another 3.4kms of the Clarence Way between Bonalbo and Urbenville. Council has received a $5 million grant through the Australian Government’s Safer Local Roads and Infrastructure Program to undertake the work, which will include improvements to drainage, replacement of culverts, and upgrades to the pavement and ride quality of three separate sections the road.

Grading crews are currently working on Bolans Road and Hootons Road, and roadside slashing is occurring on Kyogle, Williams and Findon Creek roads.

Pothole patching is happening on the Summerland Way and Gradys Creek Road.

The new Montgomerys Bridge on Iron Pot Creek Road is starting to take shape, with work to start soon on constructing the headstock. The expected completion date for the bridge is the end of August, weather permitting.

Preparatory works are continuing for the new Methvens Bridge on Gradys Creek Road, with construction of the side track still in progress.

Repairs to the final landslip on Lions Road caused by the 2022 floods are in progress, as are repairs to Lions Road. Lions Road was re-opened under traffic control on Tuesday.  Motorists are reminded that the Lions Road is a scenic drive, not a main road, and should not be used by caravans or other heavy traffic.

Once repairs to the final section of Lions Road are completed, the road rehabilitation crew will move on to Gradys Creek Road, with the repair sites under traffic control.

Council continues to monitor the landslip on Iron Pot Creek Road, while work on the Forest Road landslip is progressing  and repair work has started on a landslip on Horseshoe Creek Road.

Work on Summerland Way at The Risk and 1.5km south of the Queensland border is continuing.

Lions Road open to light traffic

The Lions Road is now open to light traffic only.
Landslip repairs near the Border Loop Lookout and ongoing road rehabilitation works are still underway, and both areas will operate under traffic control.
Drivers should expect short delays and are asked to follow all directions from onsite crews.
Delays to work on Lions Road have been caused by ongoing wet weather and a lengthy approval process with the National Parks and Wildlife Service, which is managing impacts on endangered species in the area.
Once the final section of Lions Road is completed, the road rehabilitation crew will move on to Gradys Creek Road, with the repair sites under traffic control while works continue.
Motorists are reminded that the Lions Road is a scenic drive, not a main road, and should not be used by caravans or other heavy traffic.
Council is planning further repairs later in the year to stabilise additional landslips on Lions Road caused by Cyclone Alfred. This will require a temporary re-closure of the road once funding and approvals are in place.
Council will provide as much advance notice as possible to keep residents and motorists informed.

Council wants public feedback on draft budget

A draft $64.5 million budget that provides almost $10 million for roads and bridges and another $3 million for town and village streets has been adopted by Kyogle Council for public comment.

The draft budget also includes $2 million this year and another $3 million in the forward estimates so Council can fast track its watermains replacement program in response to ongoing issues with ageing infrastructure.

Kyogle Council Mayor Cr Danielle Mulholland said the draft budget was aimed at strengthening essential services, supporting emerging needs, and positioning the community for the future.

She said Council had worked hard to ensure the draft budget was responsible while still delivering the services and projects the community needed now and into the future.

“By releasing this draft budget for public comment, we’re inviting residents to provide feedback, Cr Mulholland said.

“Their feedback is essential in shaping a final budget that reflects what matters most to our community.”

The draft budget provides $3.948 million for regional road projects including $2 million for the Clarence Way this year and a further $3 million in the forward estimates, $4.257 million for rural local roads, and $1.635 million for bridge renewals.

The draft budget also provides $7 million this year and $17 million in the forward estimates to build a new sewerage treatment plant for Kyogle.

“Council is laying the groundwork for the future with this draft budget,” Cr Mulholland said.

“Council wants to secure a future where our infrastructure keeps pace with community needs and where the Kyogle LGA continues to attract people seeking both lifestyle and opportunity.”

The draft budget also sets aside:

  • $1.793 million for landfill improvements and quarry rehabilitation works
  • $187,146 in financial assistance and community donations
  • $614,285 for the library and mobile library
  • $1.013 million parks, gardens and village maintenance
  • $946,191 for the operation of Council’s three public pools
  • $992,300 for community and cultural services which includes the Roxy Gallery, the Visitor Information Centre and community services

The draft budget includes a 4.4 percent State Government-pegged general rate increase, plus increases of 4 per cent for domestic waste charges, 7 per cent for water charges and 6 per cent for sewer charges.

The draft budget is on display for public comment until 4pm 12 May 2026. Copies of the budget can be found at Council’s administration centre at 1 Stratheden Street, Kyogle, on Council’s website here, or at Wadeville store, Woodenbong Post Office, Tabulam Post Office, Cawongla store, Mallanganee Post Office, Wiangaree Post Office, and Bonalbo Post Office.

Written submissions will be accepted until 4pm 12 May 2026 and should be sent to the General Manager, PO Box 11, Kyogle, NSW 2474 or to council@kyogle.nsw.gov.au.

Works update – 2 April 2026

The new Cedargetters Bridge on Gradys Creek Road is expected to open to traffic next week.

Once opened, the bridge crew will remove the sidetrack and complete work on the approaches.

Council’s other bridge crews are working on:

  • Methvens Bridge on Gradys Creek Road – work has started on the side track.
  • Montgomerys Bridge on Iron Pot Creek Road – work on the piers is now complete, with progress being made on the pier headstocks. Work on the concrete abutments will start after Easter.

Council’s grading and slashing crews have been active this week, working throughout the local government area.

One of the grading crews is working on Bolans Road and is expected to be finished there today. Another crew is working on Old Lawrence Road, with work there to continue until the end of next week. That grading crew will then move to Hootons Road.

Roadside slashing is occurring on Findon Creek Road and Peacock Creek Road. Fawcetts Plain Road and Tunglebung Creek Road are next to be slashed.

Repairs to the final landslip on Lions Road caused by the 2022 floods are ongoing, as are repairs to Lions Road. The work includes stabilising and sealing the road pavement. Lions Road remains closed from Murphy Standfield Bridge to the border.

Council continues to monitor the landslip on Iron Pot Creek Road, while work on the Forest Road landslip is expected to start next week. Grading on Simes Road and Forest Road is due to be completed this week,

Work on Summerland Way at The Risk and 1.5km south of the Queensland border is continuing.

On the Clarence Way, pavement work has started on the Medhurst Quarry section of the road south of Bonalbo and will continue for about five weeks. Sealing work and heavy patching is underway north of Bonalbo. It is expected to be completed, weather permitting, in May.

One-of-a-kind Mallanganee Observatory opens to the public

Mallanganee’s one-of-a-kind observatory that frames spectacular views of the constellations by night and the rolling green hills and mountain ranges of the Northern Rivers by day has opened to the public.

Situated at the top of the Richmond Range, the observatory features an armillary-like sphere built out of galvanised steel and pre-cast concrete.

The semi-enclosed design provides the perfect vantage point to take in views across the Richmond Range and beyond to the Border Ranges and Wollumbin.

At night, the dark sky and the observatory’s position on the precise latitude the centre of the Milky Way arcs directly overhead every day,  means the celestial views are breathtaking.

Kyogle Council Mayor Danielle Mulholland said the idea for the observatory had originally come from a member of the Mallanganee community and had been incorporated into the Mallanganee village master plan.

“The observatory is positioned to increase tourism to the area and cultivate Mallanganee’s standing as a destination for visitors seeking genuine nature‑based experiences, Cr Mulholland said.

“With growing interest in dark/night‑sky tourism across Australia, we are looking forward to an increase in visitor numbers.

“A tourism boost will bring real benefits not just to Mallanganee but also to its neighbouring West of the Range villages.”

The $3.34 million observatory project also included the construction of a new amenities block, upgrades to sections of Bulmers and Lookout roads, and construction of internal paths. While the observatory is now open to the public, some areas of the site have yet to be re-grassed and remained cordoned off.

Construction of the observatory was supported by a $2.067 million Regional Tourism Innovation Fund grant from the NSW Government, with Council contributing the remaining funds.

 

Lions Road update

Council is working to re-open Lions Road as soon as we possibly can, but unfortunately it won’t be in time for Easter.

It’s hoped, weather permitting, the road that will be open mid-April.

The complex work required to repair seven major landslips which occurred during the 2022 floods coupled with persistent wet weather and safety considerations have meant the road has had to remain closed longer than initial estimates.

When the road does re-open, it will be under traffic control.

Looking ahead, Council is planning further repairs later in the year to stabilise additional landslips on Lions Road caused by Cyclone Alfred. This will require a temporary re closure of the road once funding and approvals are in place.

Council will provide as much advance notice as possible to keep residents and motorists informed.

Major funding boost for Clarence Way

Council is celebrating a successful $5 million Australian Government funding application which will deliver the upgrade of another 3.4km of the Clarence Way.

Council received the $5 million through the Australian Government’s Safer Local Roads and Infrastructure Program, further strengthening the existing $47.2 million Clarence Way Upgrade Project between Sandilands and Urbenville.

Council will add $1.25 million to the $5 million to upgrade additional sections of the road between Bonalbo and Urbenville.

The works will involve improving drainage, replacement of culverts, widening the pavement to a consistent 7m wide bitumen sprayed seal, pavement strengthening, ride quality improvement, line marking, signage and delineation on a 2.4 km section of Clarence Way between Murphys Road and Mills Road at Bean Creek and another 1km section south of the Yabbra Scrub.

Kyogle Council Mayor Cr Danielle Mulholland described the funding announcement as incredible news and a wonderful outcome for Clarence Way communities and motorists alike.

“This is the result of some hard work and relentless lobbying, and we are excited to finally be able to put a tick in that box,” Cr Mulholland said.

“There will still be some work to do on the Clarence Way, but Council is committed to lobbying for sufficient funds to finalise the Clarence Way Project. It will provide residents with improved access and also potentially provide an alternate freight route by connecting Grafton through to Queensland.

“Congratulations to the staff and contractors who have undertaken the work on the Clarence Way to date, and a huge thank you to residents who have waited so patiently for this road to be upgraded.

“Council would like to thank the Australian Government for this funding and Member for Page, Kevin Hogan MP for making representations on our behalf.”

Bonalbo -based Councillor Tom Cooper echoed the Mayor saying it was fantastic news that  came on the back of the good work already done on Clarence Way by Council.

“Good roads lead to efficiencies in transport, and with the high cost of fuel now it’s more important than ever that our roads are as good as we can possibly make them for efficient travel,” he said.

Work on the additional 3.4km is expected to start in early 2027. Council is actively seeking further funding under the Safer Local Roads and Infrastructure Program to complete the upgrade of the full length of the Clarence Way.

All Council waste facilities closed over Easter

All of Council’s waste facilities – the Kyogle Landfill and village transfer stations – will be closed for the four days of Easter.
The waste facilities will be closed from Good Friday through to Easter Monday (April 3 to April 6) inclusive and will re-open as normal on Tuesday, 7 April.
Note: Council’s kerbside bin collection service will operate as normal over the holiday period.

Works update – 17 March

Council has finished another bridge!
Benns Bridge on Iron Pot Creek Road opened to traffic yesterday. Council crews are currently removing the side-track and working to rehabilitate the site. Once finished, the crew will move to Gradys Creek Road to start work on the new Methvens Bridge.
Council’s other two bridge crews are making progress on Montgomerys Bridge on Iron Pot Creek Road and Cedargetters Bridge on Gradys Creek Road.
🌉 Montgomerys Bridge — The crew is working on the eastern side headstock and will be placing the western side pier formwork this week.
🌉 Cedargetters Bridge – Steel reinforcement and formwork is being put in place on the deck this week, with Council hoping to pour the concrete deck next week, weather permitting.
Grading crews are working on Knights Road and Old Lawrence Road over the next two weeks and will then move to Dunns Road and Hootons Road. Roadside slashing is happening along Ettrick Road, Omagh Road, and Clarence Way and its sealed side roads.
Pothole patching is continuing on Clarence Way, with the Jetpatcher expected to move to Gradys Creek Road next week, weather permitting.
Repairs to landslips on Gradys Creek Road and Kyogle Road are complete, with crews now working to re-instate the sites and repair the road surfaces.
Council continues to monitor the landslip on Iron Pot Creek Road, while work on the Williams Road landslip has stopped for now due to contractor issues. The site has reopened to traffic, and works will recommence later this year.
Flood repairs to Lions Road are continuing, however the recent wet weather has delayed progress. Crews are working hard to make up for lost time, with the repairs not expected to be completed until mid-April. Lions Road remains closed from Murphy Standfield Bridge to the border.
Work to replace a flood-damaged culvert on Masons Road was due to start today and is likely to take a week to complete.
Work on Summerland Way at The Risk and 1.5km south of the Queensland border is continuing.
On the Clarence Way, Council is replacing a culvert and carrying out heavy patching north of Bonalbo and cleaning drains and replacing another culvert south of Bonalbo in the Medhurst Quarry section of the road. The funded work is expected to be completed, weather permitting, in May, with Council continuing to lobby for extra money to complete the upgrade of the entire length of the road.
Meanwhile, Council staff are taking video equipment and the roughometer out on to all roads in the local government area to measure the “roughness” of the road surfaces. The information collated is used when determining road maintenance priorities and applying for grant funding.

Works update – 5 March 2026

Council’s grading, slashing and road and bridge construction crews are all making the most of the fine weather this week.

Grading crews are working on Imesons, Rices, Richmond Range and Old Lawrence roads, while roadside slashing is happening along Kyogle, Fawcetts Plain, Sextonville and  Edenville roads as well as the Clarence Way.

Pothole patching is also happening on Clarence Way.

Council’s three bridge crews are working on:

  • Benns Bridge on Iron Pot Creek Road – The deck has been poured and the bridge approaches are now under construction. The bridge is expected to be finished at the end of next week. Once it is open to traffic, the crew will move to Gradys Creek Road to start work on the new Methvens Bridge.
  • Montgomerys Bridge on Iron Pot Creek Road – Work is progressing on capping the piles. The bridge is expected to be completed by late August.
  • Cedargetters Bridge on Gradys Creek Road – Packing beams that will accommodate the new deck have been installed, with the pre-cast girders expected to arrive on site next week. The new bridge is expected to be open to traffic at the end of April.

Repairs to landslips on Lions Road, Kyogle Road, and Gradys Creek Road are continuing with the Kyogle Road and Gradys Creek Road projects expected to be finished by the end of March.

Landslips on Lynches Creek Road and Ettrick Road have been successfully remediated.

Work to repair flood damage on Lions and Gradys Creek Roads started last month and is expected to take to the end of April to finalise.

Lions Road remains closed at the Murphy Standfield Bridge, with Council and contractors doing everything practical to re-open the road as soon as possible.

Work to widen the Summerland Way at The Risk and improve drainage and upgrade safety measures is continuing.

The Clarence Way Project is drawing to a close, with just one crew working south of Bonalbo. The funded work is expected to be completed, weather permitting, in May, with Council continuing to lobby for extra money to complete the upgrade of the entire length of the road.

Works update – 19 February 2026

Council’s bridge crews are currently working on:
  • Benns Bridge on Iron Pot Creek Road – Girders were installed last week, with the crew expected to finalise the deck formwork and steel this week ready to pour the deck next week.
  • Montgomerys Bridge on Iron Pot Creek Road – Work is continuing on the piers.
  • Cedargetters Bridge on Gradys Creek Road – The Doolan deck has been removed and headstocks are being prepared ready the installation of pre-cast girders.
Council’s grading crews are working on Ettrick Road, Hillyards/Webbs roads, Collins Creek Road, and Richmond Range Road, while roadside slashing is planned for Afterlee Road, Bentley Road, Sextonville Road, and Clarence Way.  Potholes are being patch on Omagh Road and Afterlee Road.
Landslip repairs are continuing on the Lions Road, Williams Road, Iron Pot Creek Road near Murphys Corner, Kyogle Road and Gradys Creek Road.
The remediation of landslips on Lynches Creek Road and Ettrick Road is expected to be completed by the end of February, while work to repair Gradys Creek and Lions Roads is expected to begin this week and take about two months to complete.
Lions Road remains closed at the Murphy Standfield Bridge, however it is expected to re-open at the end of March, weather permitting. It will have to close again for further landslip remediation works later in the year.
Work to widen the road, upgrade drainage, and undertake safety upgrades is continuing on the Summerland Way at The Risk. Council doing the works on behalf of Transport for NSW. The work will be ongoing for a number of months.
The Clarence Way Project is continuing with two crews working on different sections of the road south of Bonalbo. Council continues to lobby for additional funds to complete the project.

Lift the lid bin checks planned for 16-19 February

Lift the Lid bin checks will be happening across the Kyogle Local Government Area next week for green-lid FOGO bins to help our community get FOGO right and our compost clean.
The bin checks will be held:
♻️ Monday 16 February – Kyogle East
♻️ Tuesday 17 February – Geneva
♻️ Wednesday 18 February – Bonalbo Village
♻️ Thursday 19 February – Kyogle South
Doing visual checks helps identify what’s going well and where there may be confusion about what can go into the FOGO bin. The @NEWaste_NSW team will be checking and tagging bins. Those bins that are grossly contaminated will need to be taken off kerbside and the incorrect items removed before being collected, so we can ensure our compost is clean of contaminants.
It’s all about education – to reduce contamination, protect our compost, and make sure our food and garden waste is turned into something valuable, instead of going to landfill. 🌱
Here’s a quick reminder of what’s a yes and a no-go for your FOGO:
✅ YES – These can go in FOGO:
🍎 Fruit & veggie scraps
🌿 Garden clippings, leaves, grass
🍞 Bread, rice, pasta
☕ Coffee grounds & tea leaves (tea of coffee bags need to go into the red bin).
❌ NO – Keep these OUT:
🚫 Plastic bags (including ‘biodegradable’ and part-plant based bags)
🚫 Paper and cardboard
🚫 Food packaging or wrappers (even if they say compostable)
🚫 Nappies or wet wipes
🚫 Glass, metal or ceramics
🚫 Animal waste or kitty litter
This project is funded by the NSW Government through the waste levy.

Safer Internet Day

Today (10 February) is Safer Internet Day and it gives us all the opportunity to talk about what is really happening online, and think about what we can each do to make it better.
Because when we each do something small – whether that’s starting a conversation, sharing a tip or changing a habit — we make a big difference to everyone’s online experience.
There are five simple actions we can all do to make a safer internet for everyone:
1️⃣ Be kind – show empathy, respect and kindness in everyone online interaction
2️⃣ Balance time online – make space for offline connection, rest and reflection
3️⃣ Speak up – report online abuse and harmful content using the platform eSafety.gov.au/report
4️⃣ Start the conversation – talk about online safety with your networks – family, friends, colleagues and communities
5️⃣ Protect you space – use privacy settings, strong passwords or parental controls to keep your online space safe

New date for Grieve Crossing Bridge opening 

After the official opening of Grieve Crossing Bridge was postponed twice following the Bondi Beach tragedy in December, a new date has been set for this major community milestone.
The opening will now be held on site at The Risk on Tuesday, 17 February, at 10am, and the community is invited to attend.
This event will also mark:
  •  The final bridge built and funded under the NSW Government’s Fixing Country Bridges Program (Rounds 1 & 2)
  •  The 106th bridge Council has replaced since 2021 under its once-in-a-lifetime Bridge Renewal Program.
The Grieve Crossing Bridge was made possible thanks to:
  •  More than $2.5 million in funding through the Disaster Recovery Funding Arrangement’s Regional Roads and Transport Recovery Package (RRTRP), jointly funded by the Federal and State Governments
  • $2.5 million from the NSW Government’s Fixing Country Bridges Program

URGENT: Water now back on

UPDATE: 1.05PM
Great news — water has now been restored across the network. The reservoir levels are slowly rising, and our hardworking crews have flushed fresh, newly-treated water through the system to restore things back to normal.
As the supply comes back online, Council recommends running your taps for a few minutes before using the water, just to clear any residual air and discolouration that can occur after a major outage.
Council would like to thank the community for your patience and understanding.
____________________________________________________________
UPDATE 11.05AM
Council staff have repaired the broken water main, and householders may now have water in their taps intermittently. However, to assist Council flush and recharge the system, please do not turn on your taps just yet.
Council will let people know when the network is ready to be used – we are hoping it will be back on-line within a few hours.
Further updates will be provided as they are available. Council would like to thank everyone again for their patience and understanding.
______________________________________________________________
UPDATE: 9.15AM
Council has positioned a water tanker in Stratheden Street to service the public toilets at the Kyogle Memorial Hall and the Kyogle Library (disability toilet). All other public toilets in Kyogle remain closed.
Thank you again for your continued patience and cooperation as we work through the impacts of the water main break. Further updates will be provided as they become available.
_______________________________________________________________
UPDATE: 8.53AM
To support the community during this outage, Council has set up a bottled water station in the IGA carpark. Free bottled water for essential drinking supplies is available, however there is a limit of two bottles per person as supply is limited.
Please note the reservoir has been fully drained and once crews are able to turn the water back on, residents may experience further interruptions. Air pockets in the system can sometimes lead to additional breaks, and our teams will respond to these as quickly as possible.
We understand this is a difficult situation, and we appreciate the community’s patience and cooperation as crews continue working to restore the water supply safely.
More updates will be shared as soon as they are available.
______________________________________________________
Council crews are currently on site working to repair a major water main break affecting supplies this morning. Our team is doing everything possible to restore water safely, but residents should be prepared that water may not return before lunchtime.
To support essential services, a water tanker is on its way from Casino to supply the hospital. A bottled water station will also be set up for the community as soon as possible — we’ll share the location and opening time shortly.
Thank you for your patience and understanding while our crews work to get everything back up and running. We’ll keep you updated here as more information becomes available.

Change of venue for Kyogle Australia Day celebrations

Due to forecast heatwave conditions on Monday, Kyogle Australia Day Celebrations will now be held at the Kyogle Municipal Hall in Stratheden Street.
Previously advertised times and program for the celebrations remain unchanged and are:
  • 9am – Damper and a cuppa
  • 9.45am – Arrival of dignitaries
  • 10am – Official ceremony begins, followed by barbecue lunch

Works update – 21 January 2026

2026 is shaping up to be another busy year for Council.
This year’s grading program has kicked off with crews on Boorabee Creek Road and Old Lawrence Road undertaking maintenance grading. We are also doing roadside slashing on Kyogle Road.
One of our reconstruction crews is working on the Summerland Way at The Risk on behalf of Transport for NSW. The work involves widening the road, upgrading the drainage, and safety upgrades.
This work will be ongoing for a number of months.
The Clarence Way Project is continuing with two crews working on different sections of the road south of Bonalbo. The funded work is expected to be completed, weather permitting, in April, with Council continuing to lobby for extra money to complete the upgrade of the entire length of the road.
The Lions Road remains closed at Murphy Standfield’s Bridge while work to repair landslips caused by the 2022 flood is undertaken. Council is working hard to open the road as soon as possible.
Repairs to three of the four landslips on Kyogle Road are expected to be completed before Easter, while the fourth is expected to be finished mid-2026.
Other landslips are currently being repaired on: Lynches Creek Road, Iron Pot Creek Road, Williams Road, Gradys Creek Road, and Ettrick Road.
On the bridges front, work is progressing on the new Montgomerys Bridge on Iron Pot Creek Road. This bridge has been closed since November 2020 due to structural issues. The new bridge is expected to open to traffic mid-2026.
Repairs to the approaches to Geneva Bridge are underway and should be completed by the end of January.

Drop-in sessions to discuss river/wetland health

Mark the dates on your calendar and join Kyogle Council for a chat about the health of rivers and wetlands in the upper Richmond catchment.
  • Tuesday, 27 January: Supper Room of the Kyogle Memorial Institute Hall, 10am – 12pm
  • Wednesday, 28 January: Wiangaree Hall, 10am – 12pm.

Kyogle Council is working with landholders, industry and partners to understand the health of rivers and wetlands in the upper Richmond River catchment, and to prioritise areas for rehabilitation.

At these drop-in sessions you can:

  • Learn more about the project
  • Share your knowledge and experience
  • Help identify priorities for future on-ground works
    and investment

The sessions are informal, with people able to come at any time and stay as long they like.

Bridge Works and Temporary Road Closure – Edenville Road at Cedar Point

Cedar Point Bridge is closed to all traffic for approximately four weeks while Council’s contractor replaces the damaged bridge decking. Once works are complete, the current 5-tonne load limit will be removed.
𝐖𝐡𝐞𝐧:
From 7am Monday 12 January 2026 to 4pm Friday 6 February 2026
(completion date is weather dependent.)
𝐖𝐡𝐞𝐫𝐞:
Edenville Road will be closed at both the Summerland Way and Omagh Road intersections.
Alternative Route:
• Access to Omagh Road is available via Summerland Way and Anzac Drive

Expression of Interest – executive office chairs

Council has a surplus of executive office chairs that are offered for purchase via an Expression of Interest process.

Offers can be for a single unit or the entire lot of 10 chairs via the form below.

The high-back leather chairs have arms, a chrome spider wheelbase and are adjustable.

For further enquiries, please contact Council’s Manager Corporate Governance on 6632 1611.

Inspections of the chairs are not currently available, however, can be arranged upon request, following the conclusion of the EOI process.

The EOI period concludes 12 January 2026.

NOTE: The chairs must be collected from Council before the end of January.

Executive Office Chairs - Expression of Interest

Name(Required)

Stream the Council Meeting

To stream today’s Council meeting, follow this link to the Agenda and Minutes page and click on the video icon next to the 10 November Meeting event.

 

Defibrillator grants on offer

Local sporting clubs and facility owners have the chance to receive a grant of up to $3000 to install an Automated External Defibrillators (AEDs) and associated equipment.
The grants are available through the NSW Government’s Local Sport Defibrillator Grant Program.
An AED is a device that is used in conjunction with Cardio-Pulmonary Resuscitation (CPR) and delivers a controlled shock to an individual experiencing cardiac arrest, increasing their chances of survival.
Applications for grants opened on 25 September 2025 and will close upon funding allocation being exhausted or at 1 pm on 1 December 2025 (whichever is earlier).

Council meetings to be livestreamed

Exciting news – for the first time ever, Kyogle Council will live stream its monthly Council meeting today (Monday, 13 October).
To watch the livestream, visit the Agendas and Minutes page on the website to access the live stream link.
This is Council’s first attempt at live streaming, and while we don’t anticipate any problems, there could be some bumps along the way. Rest assured, we will be doing our best to bring you a smooth and accessible experience.
Council appreciates your patience and support as we take this exciting step toward greater transparency and community engagement.

Public Holiday Arrangements

Due to the Labour Day Public Holiday on Monday and Council’s Union Picnic Day on Tuesday, please be advised of the following closures:
🏢 Council’s Administration Centre – closed Monday and Tuesday
♻️ Kyogle Waste Facility – closed Monday and Tuesday
🚛 Woodenbong Transfer Station – closed Tuesday
📖 Kyogle Library – closed Monday only, operating as normal on Tuesday
All facilities will resume normal operations on Wednesday.  Thank you for your understanding.

Council plans to build multi-purpose community facility/sports hall

Kyogle Council is planning to build stage one of a multi-purpose community facility that provides sport and leisure, cultural and recreational opportunities for people of all ages and can also serve as an evacuation centre during emergencies.

The proposed Kyogle Memorial Recreation Centre will provide flexible spaces that at its heart is a contemporary sports and youth activities hall complemented by activity rooms, an office, and modern amenities including a  parents room — to view the design plans click here.

Council is planning to build the Rec Centre on Council land known as Memorial Park which has as its central feature the Kyogle War Memorial and also accommodates the existing Youth Centre which operates part time from a small building.

It is proposed that:

  • A wide range of sports could be played at “Rec Centre” including netball, basketball, volleyball, futsal, pickleball, badminton
  • The Rec Centre would be available for use by local primary and secondary schools as well as youth groups during and outside of school hours
  • The flexible activity rooms, which include a kitchenette, could be used as two smaller or one larger meeting room
  • These rooms could be adapted to host cultural programs, music, youth activities, and events for all ages
  • The Rec Centre’s design honours the existing memorial space, ensuring it remains a focal point during ANZAC Day, Remembrance Day and other commemorations
  • The Rec Centre would become a wet weather alternative gathering point for events at the Cenotaph
  • During emergencies, the building would serve as an evacuation centre, linking to the existing commercial kitchen in the Community Centre on Bloore Street
  • The design features a covered concrete forecourt and covered entryway/ramp
  • A new path would link the Rec Centre to Bloore Street and the Community Centre
  • The Rec Centre forms stage 1 of what will be a larger facility including a gym and indoor pools
  • Future stages would be built as funding becomes available.

A development application for the proposed Rec Centre is on public exhibition.