Works update – 11 June 2026
Council is pressing on with its planned works, despite the persistent wet weather which continues to soak the region.
The concrete deck on the new Methvens Bridge was poured last week and the crew are installing the barrier rail as rain showers allow. Council hopes to have the bridge open to traffic by the end of the week, but that will be dependent on the weather.
Once traffic can use the bridge, Council will remove the side track and install guardrail.
The new Montgomerys Bridge also is taking shape, with installation of the centre span girders scheduled for this week. Each girder measures 24.5m in length and weighs more than 29 tonnes.
The installation process is a highly coordinated operation involving Council, the transport contractor and the crane operator. Each of the pre-cast girders requires escorted transport on extendable trailers from Brisbane and the use of a 250-tonne crane to position them on the bridge.
Following installation of the girders, the crew will commence construction of the final abutment.
Piling works are progressing on the Clarks Lane footbridge, with one pile installed on the Clarks Lane side of the river.
Once all the piles on that side are completed, the piling rig will shift to the Daleys Lane side of the river.
Work is continuing on flood damage repairs including:
- Landslip remediation on Lions Road – earthworks have been completed, with concreting and planting of native trees to be undertaken.
- Landslip remediation on Gradys Creek Road – mostly completed, with the re-instating of the job site the last of the works to be undertaken.
- Road repairs Lions Road – sealing works are almost complete, line marking still outstanding.
- Road repairs Gradys Creek Road –overlay and drainage works are progressing with stabilising to happen next week if the weather allows.
- Landslip Iron Pot Creek Road – Council is monitoring the slip daily and reinstating the road when necessary.
- Landslip remediation on Forest Road – work on the slip is completed, however a culvert still has to be installed.
- Landslip remediation on Horseshoe Creek Road – work to replace a pipe was scheduled to occur this week but was weather dependent.
- Landslip remediation on Hillyards Road – repairs are due to start next week but are weather dependent.
- Preliminary works are being carried out on a landslip on Baileys Bridge Road and a second landslip on Gradys Creek Road.
Meanwhile, Council, on behalf of Transport for NSW, is undertaking heavy patching works on the Summerland Way south of Wiangaree.
On the local roads front, a construction crew is undertaking rehabilitation works on Lindsay Creek Road and grading crews are working, when the weather allows, on Hootons Road and Collins Creek Road. Roadside slashing is happening on Fawcett Plain Road and Old Grafton Road.
Potholes are being patched on the Bruxner Highway, while kerb and gutter works are continuing in Koorelah Street, Bonalbo.
On the Clarence Way, guardrail installation and line marking was scheduled to start at the end of this week, however the work is dependent the weather.


























